Arta Grafică printing house, Bucharest · 600 kWp plant + 215 kWh storage · 2024
In industry, energy is not an operating detail. It is part of the cost of production. The Arta Grafică project shows how the roof of a hall can be used to integrate solar production into an existing energy infrastructure.
The configuration
- 926 AIKO panels of 650 Wp.
- Six 100 kW Huawei inverters.
- A 215 kWh storage system.
The configuration brings two important questions for industrial operators into one investment: how much energy can be generated on site, and how the available energy can be managed more flexibly.
What this project shows
PV + BESS integration should be treated as one electrical solution, not as two separate purchases. For every new client, the capacity, battery size and control strategy are sized on real consumption.